Contrary to popular belief, yes, we're still making PCBs! Reinforcements of components arrive...
...and are quickly put to good use, with several more input & output boards assembled, cleaned & tested
With more PCBs made, a quick view shows that we're 50% of the way to filling the final two racks
More tag block soldering is called for; Jamie does the honours while Tom helps test around the front
Meanwhile, Peter continues to terminate the cables at the PCB end, in readiness for more testing
Testing reaches Uffington loop...worthy of such a cake-based celebration! The look westwards shows just how far we've come
More parts arrive, allowing the telephone concentrator keyboards to have complete button sets again - can you spot the new ones?
Paul tackles the shelving move, cleaning & tidying our stocks; this will help allow the panel to be moved backwards to its final position in due course
Front doors almost in place
David, with cutters to the fore, trims back cable ties from tidied cable runs & works on the labelling system.
Tiles now carefully sorted & stored on polystyrene sheets for potential future use.
Another working day: John begins by stripping down our spare dominos stock into their respective pieces.
Meanwhile, Peter continues the terminating & soldering of 8-core cables at the tag blocks...plenty of practice still available for those that want it!
The finished article: an easy to identify, very neat end result - a great improvement!
With the Panel behind the external wall to the right, substantial restoration works to the air raid shelter are evidenced here.
...then smooths the concrete to the desired finish; a good job well done!
Richard (GWS's Civil Engineering Manager), having put in place some complex shuttering, pours the concrete for the front double-door sill...
Building works continue, with the two loft areas receiving their flooring.
As the flooring is completed, the electricians begin to install the required conduit for lighting, alarms, etc.
PCBs continue to be received & tested before being installed in the panel - certainly a railway theme accompanying the parcel here...
...whilst other completed PCBs proudly state their country of origin!
Behind the panel, the all-important earthing wire is installed...
...whilst to the front of the panel, SPS members make great progress with inserting the microchips into the PCBs & testing the finished product.
Outside, the new pathway boundary wall takes shape, with further works on the air-raid shelter (extreme left) also continuing apace.
Meanwhile, the Bristol Group install the first lamps back into their Bristol East panel - can you spot them among all that daylight?
Behind the panel, John installs the first PCB into Rack 1, the final rack to receive them - well done that man!
There's still plenty of tag block work to complete, yet Jamie's rapid soldering skills mean that Swindon Station is getting ever closer.
More installation & fault-finding in progress, with Danny to the fore!
The computer desk comes into its own as panel testing continues...
...whilst Peter gets to grips with making as many power jumper cables for the PCBs as possible.
Further PCB installation, with the end of the panel very much in sight - Jerry carefully threads the ribbon cable down towards the correct socket on the TC64 units.
20170708 115226
20170708 113636
20170708 144704
20170708 124444
20170708 124306
IMG 7038
IMG 7028
IMG 7026
IMG 7024
IMG 7025
IMG 7021
DSC 0556
DSC 0555
DSC 0553
DSC 0552
DSC 0551
IMG 7043
IMG 7041
IMG 7039
IMG 2760
IMG 2759
IMG 2758
IMG 2757
IMG 2761
IMG 2925
IMG 2924
IMG 2923
IMG 2922
IMG 2921
IMG 2920
IMG 2919
IMG 2918
IMG 2927
IMG 2926
IMG 20170708 131049
IMG 20170708 131044
IMG 20170708 131035
DSC 4928
DSC 4922
DSC 4921
DSC 4920
DSC 4919
DSC 4918
DSC 4917
DSC 4915
DSC 4913
DSC 4910
DSC 4909
DSC 4908
DSC 4907
DSC 4903
DSC 4901
DSC 4893
DSC 4886
DSC 4883
DSC 4882
DSC 4881
DSC 4880
DSC 4879
DSC 4878
DSC 4876
DSC 4873
DSC 4871
DSC 4870
DSC 4869
DSC 4868
DSC 4866
DSC 4864
DSC 4863
DSC 4860
DSC 4859
DSC 4858
DSC 4856
DSC 4854
DSC 4850
DSC 4848
IMG 20170708 141911
IMG 20170708 134201
IMG 20170708 131448
IMG 20170708 131427
IMG 20170708 131216
19222879 2327053890853229 3860358126456957132 o
19787477 2327053874186564 5647308733860186941 o
19944569 2326015910957027 1626030163596937052 o
19956648 2327053897519895 3078273689233204095 o
19984096 2327053904186561 2562373270103060351 o
19787279 2327054120853206 4106694513681705987 o
19787478 2327054194186532 9056901432563396751 o
19944255 2327054247519860 2913856681271103505 o
19955979 2327054217519863 3441977963370355933 o
19800959 2327054007519884 2334489724168801333 o
image1
image4
image3
image2
DSC 0155
DSC 0154
DSC 0153
DSC 0151
DSC 0150
DSC 0140
DSC 0137
DSC 0135
DSC 0134
DSC 0133
DSC 0132
DSC 0129
DSC 0128
DSC 0125
DSC 0124
DSC 0123
DSC 0118
DSC 0117
DSC 0116
DSC 0115
DSC 0114
DSC 0113
DSC 0112
DSC 0111
DSC 0107
DSC 0104
DSC 0103
DSC 0102
DSC 0101
DSC 0100
DSC 0099
DSC 0098
DSC 0096
DSC 0095
DSC 0094
DSC 0092
DSC 0088
Looking out through the front doors
Loft space above Swindon Room
IMG 20170709 151125339
18835617 2298662147025737 5351825391619793250 n
18920432 2298662117025740 7715164036857369911 n
P1070212
P1070184
P1070183
P1070181
P1070180
IMG 20170527 160654484 HDR
IMG 20170527 155813703
IMG 20170527 155808040
IMG 20170527 155801371
IMG 20170527 155757984
IMG 20170527 155751763
IMG 20170527 155734593
IMG 20170527 155231989
IMG 20170527 155230212
IMG 20170527 155228784
IMG 20170527 155221305
IMG 20170527 155026065
IMG 20170527 155013435
IMG 20170527 150929399
IMG 20170527 150759401
IMG 20170527 150752506 HDR
IMG 20170527 120651751
IMG 20170527 120205023
IMG 20170527 120151141
IMG 20170527 120143628
A test of the now-attached manual levers, controlling two semaphores for visitors to try their hand at.
Further building electrics being installed
The front entrance path progresses...
...whilst the side path, seen here from the rear of the signalling building, is all but complete - excellent work!
20170303 170529
20170303 114127
20170302 110000